- lessons_learned:
- description:
- Project design While the specific circumstances of this projects development were unusual and required the project to be approved before the usual consultation and design work had been done, this contributed greatly to the delay in project implementation. In the future, when circumstances lead to the initial approval of a project that needs subsequent more detailed design work, either the design process needs to be completed much sooner (i.e. within three months, not after fifteen) or a more realistic implementation schedule needs to be set (either by extending the period of implementation or reducing the technical and/or geographic scope of activities).
- context:
- Project development and planning
- success:
- N/A
- challenges:
- Complex multi-regional projects require more time for detailed activity planning. If this planning consumes too much of the time available for implementation, results can be negatively affected.
- administrative_issues:
- N/A
- comments:
- Targeted users/beneficiaries: Project designers
- url:
- https://analyticstest.ilo.org/ievaldiscovery/lessons/216558
- themes:
- theme:
- Planning and programme design
- category:
- Organizational issues