Go to ILO main website
Back to index

Global action to improve the recruitment framework of labour migration - Final Evaluation

eval_number:
2629
eval_title:
Global action to improve the recruitment framework of labour migration - Final Evaluation
location:
region:
Americas
country:
Mexico

region:
Inter-Regional
country:
Inter-Regional

region:
Africa
country:
Madagascar

region:
Asia and the Pacific
country:
Malaysia

region:
Asia and the Pacific
country:
Nepal

region:
Arab States
country:
Lebanon

region:
Asia and the Pacific
country:
Pakistan

region:
Africa
country:
Kenya

region:
Americas
country:
Guatemala

region:
Asia and the Pacific
country:
Sri Lanka

eval_url:
https://analyticstest.ilo.org/ievaldiscovery/eval/2629
lessons_learned:
description:
Based on the ILO’s experience of implementing the REFRAME project in multiple countries, the evaluation team observed that project effectiveness can be affected both positively and negatively by the presence of other projects working in similar thematic areas in a given country.
context:
REFRAME is a project that works with tripartite constituents in establishing fair recruitment initiatives. REFRAME does so in multiple countries in different regions, namely in Sri Lanka, Pakistan, Madagascar, Mexico and Guatemala. In countries where REFRAME was seen as the only project addressing issues of labour migration, REFRAME had privileged access to stakeholders who were receptive to its interventions. The project’s effectiveness was challenged in countries where REFRAME was competing with other ILO projects also working on labour migration issues for constituents’ attention and space. The implementation of REFRAME was observed to be more effective in countries where there is a vacuum in terms of initiatives already being implemented in the same thematic area.
success:
A selection of countries for implementation where stakeholders are available to engage with the ILO in a given thematic area can result in enabling project effectiveness since stakeholders are receptive and available to engage with the project.
challenges:
A selection of countries for implementation where stakeholders are already significantly engaged with the ILO in a given thematic area can result in limiting space and availability to engage with a new ILO project, and hence decrease the project’s effectiveness.
administrative_issues:
None
comments:
Project managers responsible for selecting countries of implementation, particularly projects that are implemented in multiple countries.
url:
https://analyticstest.ilo.org/ievaldiscovery/lessons/222726
themes:
theme:
Programme implementation
category:
Organizational issues