Inclusive Growth through Decent Work in the Great Rift Valley - Midterm Evaluation

eval_number:
2891
eval_title:
Inclusive Growth through Decent Work in the Great Rift Valley - Midterm Evaluation
location:
region:
Africa
country:
Kenya

eval_url:
https://analyticstest.ilo.org/ievaldiscovery/eval/2891
lessons_learned:
description:
Arrangements for projects such as the PPDP, need funding for the preparations that are necessary prior to the projects´ start up Like so many other ILO Projects, the Project used the inception phase mainly to build partnerships, mobilise partners to commit to the funding strategies and objectives, and to set up the governance committees. However, it took a lot of time (several years) prior to this stage could even start up, during which ILO (and consultants), Sida/Swedish Embassy and Akiira developed the ideas - preparations which were costly.
context:
Some key persons had to leave the preparatory process which caused delays in getting the design in place and start up the Project.
success:
Had specific funding been available for the project development period, the preparatory phase would have been smoother and faster and continuity of the process could have been secured.
challenges:
n/a
administrative_issues:
ILO and donors could agree to spend funds for Project preparatory phases.
comments:
N/A
url:
https://analyticstest.ilo.org/ievaldiscovery/lessons/239425
themes:
theme:
Planning and programme design
category:
Organizational issues