Migrant Rights and Decent Work (MiRiDeW) - Final Evaluation

eval_number:
2955
eval_title:
Migrant Rights and Decent Work (MiRiDeW) - Final Evaluation
location:
region:
Asia and the Pacific
country:
Nepal

eval_url:
https://analyticstest.ilo.org/ievaldiscovery/eval/2955
lessons_learned:
description:
The log-frame of the project must highlight risks, assumptions and mitigation strategies under all the result areas. This is in context of the MiRiDeW’s log-frame wherein the risks, assumptions and mitigation strategies were not identified under its two outcomes, i.e. Outcome 1 and 2. This significant impacted the project’s progress as evident from the results achieved under the project. Further, the turnover of project officials must also be included in the risks, so that suitable mitigation systems are in place to lessen the impact of change of project officials.
context:
Relevant to all projects especially while developing proposals.
success:
Identification of all the relevant risks and assumptions can help in developing strategies to deal with any future blockages.
challenges:
If the results framework do not identify risks and assumptions for all the result areas, relevant mitigation strategies are not developed for such result areas which influences their performance.
administrative_issues:
Relevant to the design of the future projects.
comments:
ILO officials
url:
https://analyticstest.ilo.org/ievaldiscovery/lessons/242488
themes:
theme:
Planning and programme design
category:
Organizational issues