ACTION/Portugal (Phase 2): Strengthening of the Social Protection Systems of the PALOP and Timor-Leste - Final evaluation (English)
- eval_number:
- 3097
- eval_title:
- ACTION/Portugal (Phase 2): Strengthening of the Social Protection Systems of the PALOP and Timor-Leste - Final evaluation (English)
- location:
- region:
- Inter-Regional
- country:
- Inter-Regional
- eval_url:
- https://analyticstest.ilo.org/ievaldiscovery/eval/3097
- lessons_learned:
- description:
- The physical presence of experts dedicated to the Project in the beneficiary countries favours the establishment of relationships of trust with the beneficiary entities, and potentiates more significant and sustainable advances in the proposed objectives, especially in the pandemic context.
- context:
- The Project Management structure did not include permanent experts posted in all beneficiary countries.
- success:
- In countries where there was a permanent physical presence of ILO project experts or focal points (e.g. Cape Verde, Mozambique) there tended to be more progress, such as the Statistical Bulletin on Social Protection, published in Mozambique, and in imminent publication in Cape Verde.
- challenges:
- In countries where there was no permanent physical presence of project experts (e.g. Angola, Guinea-Bissau) there tended to be less progress in relation to the project's objectives.
- administrative_issues:
- n/a
- comments:
- SOCPRO/ILO, GEP-MTSSS
- url:
- https://analyticstest.ilo.org/ievaldiscovery/lessons/246674
- themes:
- theme:
- Programme implementation
- category:
- Organizational issues