Back to index
Decent Work Opportunities for Refugees and Host Communities in Türkiye - Final evaluation
- eval_number:
- 3473
- eval_title:
- Decent Work Opportunities for Refugees and Host Communities in Türkiye - Final evaluation
- location:
- region:
- Europe and Central Asia
- country:
- Türkiye
- eval_url:
- https://analyticstest.ilo.org/ievaldiscovery/eval/3473
- lessons_learned:
- description:
- The output-based, rather than activity-based planning, hinders efficiency and impedes effectiveness of the intervention, as well as limiting the identification and high-level engagement of stakeholders.
A substantial effort is needed to develop activities to reach the outputs. Those efforts necessitated identifying right stakeholders and their engagement to the relevant activities. The time pressure caused loss of efficiency and effectiveness in this dimension. This resulted limited access to potential stakeholders, and constituents, unsuccessful attempts, lower quality results and underutilization of their capacity.
- context:
- The refugee problem has been on top of the agenda of Türkiye more than a decade. The challenge also resulted in capacity development for related constituents and stakeholders. However, there’s no systematic mechanism bringing all efforts and parties together.
The preconditions are presence of numerous stakeholders dealing with refugees and decent work opportunities. These actors are also interested in linking their efforts to those of an international organization, ILO namely. They express that they are open to learn more, and they want to have wider role/engagement with such interventions than being taking limited activity-specific roles.
- success:
- N/A
- challenges:
- The absence of activity-based approach causes development of activities for long period of time, to reach outcomes.
In time limitation limited number of, mainly previous ones, can be contacted. The capacity of some stakeholders is under-utilized.
The efforts needed for supporting stakeholders to achieve better quality results and for ensuring higher level engagement
- administrative_issues:
- N/A
- comments:
- ILO
- url:
- https://analyticstest.ilo.org/ievaldiscovery/lessons/256366
- themes:
- theme:
- Planning and programme design
- category:
- Organizational issues
Skip to top