Promotion of Decent Work in Southern African Ports (phase II) - Final Evaluation
- eval_number:
- 2575
- eval_title:
- Promotion of Decent Work in Southern African Ports (phase II) - Final Evaluation
- location:
- region:
- Africa
- country:
- Africa - regional
- eval_url:
- https://analyticstest.ilo.org/ievaldiscovery/eval/2575
- recommendations:
- title:
- PMU (project management unit) to be more exertive on planned implementation plans and timely action on the top management in both TPT and MPDC as well as at the terminal levels.
- url:
- https://analyticstest.ilo.org/ievaldiscovery/recommendations/10981
- action_plan:
- Support the project management unit towards planned implementation project activities.
- comments:
- None
- date:
- 2016-01-01 00:00:00.0
- progress:
- Achieved
- management_response:
- Completed
- information_source:
- Country Office
- admin_units:
- DWT/CO-Pretoria
- project_symbols:
- SAF/13/01/MUL
- themes:
- theme:
- Organizational issues
- category:
- Programme implementation