Cluster Independent Mid-term Evaluation of RMGP II and BWB and its affiliated projects - Midterm evaluation
- eval_number:
- 3032
- eval_title:
- Cluster Independent Mid-term Evaluation of RMGP II and BWB and its affiliated projects - Midterm evaluation
- location:
- region:
- Asia and the Pacific
- country:
- Bangladesh
- eval_url:
- https://analyticstest.ilo.org/ievaldiscovery/eval/3032
- recommendations:
- title:
- Strengthen overall project management
• Review planned down-scaling of project personnel to keep key personnel on longer
• Conduct more regular stock-taking exercises (example January 2020 analysis), especially to adapt existing strategies to Coronavirus-induced industry challenges
- url:
- https://analyticstest.ilo.org/ievaldiscovery/recommendations/14680
- action_plan:
- Develop change management plan that includes HRD and Capacity Development plans
Use the Learning Hub to provide TOT training to a selected cohort of LIs, to be appointed by DIFE.
- comments:
- RMG Cluster strategy, proposed outcomes and organogram to be aligned to determine staffing needs
Synergies need to be found between RMGP II and BWB, particularly in work relating to the labour inspection process and safety committee training.
Areas of collaboration have been identified in training of LIs on OSH in the workplace in Covid situation
- date:
- 2021-04-22 00:00:00.0
- progress:
- Partially achieved
- management_response:
- Partially Completed
- information_source:
- Country Office
- admin_units:
- CO-Dhaka
- project_symbols:
- BGD/19/05/MUL
- themes:
- theme:
- Organizational issues
- category:
- Results-based management